Ten men take 4 days to complete the task of tarring a road. How many days would 8 men take?

1 Answer

+1 vote
by (32.4k points)
selected by
 
Best answer

Let us suppose that 8 men require x days to tar the road.

Number of days required by 10 men to tar the road 

= 4 

The number of men and the number of days required to tar the road are in inverse proportion.

∴ 8 men will require 5 days to tar the road.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.