If t1=Time at which water is first added to cement, t2=Time when needle fails to penetrate 5 mm to 7 mm from bottom of the mould, t3=Time when the needle makes an impression but the attachment fails to do so, then what is initial setting time?

(a) t2-t1

(b) t2+t1

(c) t3-t1

(d) 2*t1

1 Answer

0 votes
by (120k points)
selected by
 
Best answer
The correct choice is (a) t2-t1

For explanation: t2-t1 is the formula to determine the value of the initial setting time of concrete for further process.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.