Use app×
QUIZARD
QUIZARD
JEE MAIN 2026 Crash Course
NEET 2026 Crash Course
CLASS 12 FOUNDATION COURSE
CLASS 10 FOUNDATION COURSE
CLASS 9 FOUNDATION COURSE
CLASS 8 FOUNDATION COURSE
0 votes
123 views
in General by (106k points)
closed by
Negative value of cost variance (CV) of construction project indicates that project is
1. Behind schedule 
2. Over budget
3. Under budget 
4. On schedule

1 Answer

0 votes
by (106k points)
selected by
 
Best answer
Correct Answer - Option 2 : Over budget

Concept-

Cost Variance (CV):

  • Cost variance is basically related with the budget of the project.
  • Cost variance is the difference of the actual cost and the expected cost.
  • Cost Variance is calculated by taking the difference of the Earned Value and the Actual Cost.
  • If the cost variance is positive then the project is under budget.
  • If the cost variance is zero then the project is on budget.
  • If cost variance is negative then the project is over budget.

Schedule Variance (SV):

  • Schedule variance basically related with the scheduled time for the project.
  • Schedule variance is the measurement of deviation of consumed time from the scheduled time.
  • Scheduled Variance is calculated by taking difference between Earned Value and Planned Value.
  • If schedule variance is negative then the project is behind schedule.
  • If the schedule variance is positive then the project is ahead of schedule.
  • If the schedule variance is zero then the project is on schedule.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

Categories

...