A certain sum of money is sufficient to pay M's wages for 20 days and N's wages for 30days. For how many days the same amount of money is sufficient to pay wages for both?
1. 12 days
2. 10 days
3. 20 days
4. 15 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 1 : 12 days

Calculation:

Let amount of money be Rs.a.

M's 1 day's wages = Rs.(a/20)

N's 1 day's wages = Rs.(a/30)

(M + N)'s 1 days wages = a/20 + a/30 = Rs.(a/12)

The same amount of money is sufficient for a/(a/12) = 12 days

∴ The same amount of money is sufficient to pay both for 12 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.