Correct Answer - Option 3 : Programme Evaluation and Review Technique
Concept:
PERT stands for "Programme Evaluation and Review Technique". This network model is used for project scheduling.
Difference between PERT and CPM (Critical Path Method)
PERT
|
CPM
|
1. Probabilistic approach
|
1. Deterministic approach
|
2. Three-time estimate
|
2. One - time estimate
|
3. Event oriented network model
|
3. Activity-oriented network model
|
4. The slack concept is used
|
4. Float concept is used
|
5. Project crashing is not possible
|
5. Project crashing is possible
|
6. Deals with probabilistic time estimates
|
6. Deals with deterministic time estimates
|