Correct Answer - Option 1 : 15 days
Given:
20 men can complete a work in 15 days.
Formula used:
Work = Efficiency × Time
Calculation:
Total work = 20 × 15 unit
⇒ 300 unit
Now, 90% of 300 units = (90/100) × 300 unit
⇒ 270 unit
First 5 days work by 20 men = 20 × 5 unit
⇒ 100 unit
Followed 5 days work by 18 men = 18 × 5 unit
⇒ 90 unit
Followed 5 days work by 16 men = 16 × 5 unit
⇒ 80 unit
Total work in 15 days = (100 + 90 + 80) units
⇒ 270 units
∴ 90% of the work is completed in 15 days.