Correct Answer - Option 3 : 3000
The correct answer is option 3
Formula:
The total cost of the project = Total development cost + Total maintenance cost
Calculation:
Let p1 be the LOC using L1 and p2 be the LOC using L2.
Total cost of the project using L1 = (p1/1000) x 70,000 + (10 x 1,00,000) = 70p1 + 10,00,000
Total cost of the project using L2 = (p2/1000) x 90,000 + (10 x 40,000) = 90p2 + 4,00,000
Given that p2 = 3xp1
=>70p1 + 10,00,000 = 90p2 + 4,00,000
=>70p1 + 10,00,000 = 270p1 + 4,00,000
=> 200p1 = 6,00,000
=> p1 = 3000