Pre-stressed concrete is more desirable in case of
1. Cylindrical pipes subjected to internal fluid pressure
2. Cylindrical pipes subjected to external fluid pressure
3. Cylindrical pipes subjected to equal internal and external fluid pressures
4. Cylindrical pipes subjected to end pressures

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 1 : Cylindrical pipes subjected to internal fluid pressure

Explanation:

(i) Pre-stressed concrete is a form of concrete where initial compression is given in the concrete before applying the external load so that stress from external loads are counteracted in the desired way during the service period.

(ii) This initial compression is introduced by high strength steel wire or alloys (called ‘tendon’) located in the concrete section.

(iii) When the cylindrical pipes are subjected to internal fluid pressure the hoop stress and circumferential stress acting on it will be tensile in nature. So for these pipes pre-stressed concrete is more desirable so that the stresses will be counterbalanced.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.