Correct Answer - Option 2 : 45 bags
Concept:
i) Wet volume of concrete = 1 m3
ii) Dry volume of concrete should be taken to be 54 % more than its wet volume
iii) Concrete ratio = 1:3:6, which implies for 1 cubic meter of concrete contains 1 part cement, 3 part sand or fine aggregates and 6 parts coarse aggregates.
iv) 1 bag of cement = 50 kg of cement
v) Density of cement = 1440 kg/m3
Calculation:
Dry volume of concrete = 1.54 x 10 m3 = 15.4 m3
Volume of cement required:
\(V = \frac{1}{10} × 15.4 = 1.54\;{m^3}\)
Weight of cement required:
W = Volume of cement × Density of cement = 1.54 × 1440
Weight of cement required = 2217.6 kg
Number of cement required:
\(N = \frac{{Total\;weight\;of\;cement\;required}}{{Weight\;of\;1\;bag\;of\;cement}}\)
∴
\(N = \frac{{2217.6}}{{50}} = 44.35\;bags\approx45\;bags\)