Correct Answer - Option 3 : 7
Given:
Time taken by X to complete the work alone = 10 days
Time taken by Y to complete the work alone = 15 days
Time taken by Z to complete the work alone = 60 days
Formula Used:
Efficiency = Total work/Time taken
Calculation:
Let the total work be 60x units (LCM of 10,15, 60)
Efficiency of X = 6x units/day
Efficiency of Y = 4x units/day
Efficiency of Z = x units/day
Work done in 5 days by X and Y = (6x + 4x) × 5
= 50x units
⇒ Remaining work = 60x – 50x = 10x units
This work is completed by Y and Z
Time taken to complete the remaining work = 10x/[(4x + x)]
= 10x/5x = 2 days
Total time taken to complete the whole work = 5 + 2 = 7 days
∴ The total time taken to complete the whole work is 7 days