Correct Answer - Option 2 : 7.5
Given:
Ratio of the number of days required by Pramod and Vallabh to finish the work alone = 2 ∶ 3
Number of days required to complete the work together = 6
Number of days they worked together = 3
Formula Used:
If a person takes x days to complete a work alone, the part of the work he completes in 1 day = 1/x
Calculation:
Let the number of days required by Pramod to complete the work alone = 2x
So, the part of the work completed by Pramod in one day = 1/2x
Let the number of days required by Vallabh to complete the work alone = 3x
So, the part of the work completed by Vallabh in one day = 1/3x
Hence, when they work together for a day, the part of the work they complete is given by:
(1/2x) + (1/3x) = 1/6
⇒ x = 5
Hence, the number of days required by Pramod to complete the work alone = 2 × 5 = 10
Also, the number of days required by Vallabh to complete the work alone = 3 × 5 = 15
So, when they work together for 3 days, the part of the work completed = 3 × (1/6) = 1/2
So, the remaining work to be completed by Vallabh alone = 1- (1/2) = 1/2
Hence, the number of days required by Vallabh to finish the remaining work alone is given by:
15/2 = 7.5
∴ The number of days required by Vallabh to finish the remaining work alone is 7.5