For completion of a project, the critical path of the network represents
1. minimum time
2. maximum time
3. maximum cost
4. minimum cost

1 Answer

0 votes
by (240k points)
selected by
 
Best answer
Correct Answer - Option 1 : minimum time

Concept:

From the activity network representation, it can be analysed that the minimum time to complete the project is the maximum of all paths from start to finish.

So, the longest path will represent the critical path for the network, and it will represent the minimum possible duration required to complete the project.

The critical path will be the longest path in the network requiring the maximum amount of time, but it will represent the minimum duration that is required to complete all the activities i.e. completion of a project.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.