Correct Answer - Option 1 :
\(19\frac{1}{2}\) days
Given:
Time is taken by Akash and Bhuvan to finish the work = 13 days
Number of days after which Akash left work = 5 days
Number of days taken by Chethan and Bhuvan to finish work after Akash left = 6 days
The efficiency of Bhuvan = 2 × efficiency of Akash
Concept used:
Work = time × efficiency
Calculation:
The ratio of efficiency of Bhuvan to Akash = 2 ∶ 1
Then, total work done by both together = 13 × (2x + 1x) = 39x
Let the efficiency of Chethan be ‘c’.
Total work = (Akash + Bhuvan) × 5 + (Chethan + Bhuvan) × 6
⇒ 39x = 3x × 5 + (c + 2x) × 6
⇒ c + 2x = 4x
Or, efficiency of Chethan = 2x
Time taken by Chethan to finish the work alone = 39x/2x = \(19\frac{1}{2}\) days.
∴ Chethan will take \(19\frac{1}{2}\) days to finish the work.