Correct Answer - Option 4 : 6 hours per day
Given:
30 men working 8 hours per day can dig a pond in = 16 days
Formula:
M1 × T1 × D1 = M2 × T2 × D2
Calculation:
M1 = 30 men, T1 = 8 hrs, D1 = 16 days, M2 = 32 men, D2 = 20 days
According to the formula
30 × 8 × 16 = 32 × T2 × 20
⇒ T2 = (30 × 8 × 16)/(32 × 20)
∴ T2 = 6 hrs.