Correct Answer - Option 3 : 18 days
Given:
48 Persons make a bridge in 15 days working 6 hours a day.
Concept Used:
M1 × H1 × D1 = M2 × H2 × D2
Where,
M = No of persons
H = Hours of working in a day
D = No of days to complete the work
Calculation:
M1 × H1 × D1 = M2 × H2 × D2
⇒ 48 × 15 × 6 = 30 × 8 × D2
⇒ D2 = 18 days