2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can do 2 men and 1 boy the work ? 

(a) 8 days 

(b) 7 days 

(c) 25/2 days 

(d) 2 days

1 Answer

+1 vote
by (80.0k points)
selected by
 
Best answer

Correct option (c) 25/2 days

Explanation:

According to question, 

(2 men + 3 boys)× 10 days 

= ( 3 men +2 boys)×8 days 

20 men + 30 boys = 24 men + 16 boys 

 2 men = 7 boys 

2 men + 1 boy = 7 boys + 1 boys = 8 boys 

From ist line :

2 men + 3 boys  7 boys + 3 boys  10 boys given

10 boys can do a piece of work in 10 days 

1 boys can do a piece of work in 10 × 10 

8 boys can do a piece of work in 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.