Two workers A and B working together completed a job in 5 days. If A had worked twice as efficiently as he actually did, the work would have been completed in 3 days. To complete the job along, A would require: 

(a) 26/5 days 

(b) 25/4 days 

(c) 15/2 days 

(d) 35/4 days

1 Answer

+1 vote
by (80.0k points)
selected by
 
Best answer

Correct option (c) 15/2 days

Explanation:

Assume A eff. is 2 units B’s is 1 units. 

So it satisfies the equation of both cases 

So actual efficiency of A is 2 Units/day

A alone complete the work in

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.