Correct option (a) 48 days
Explanation:

According to questions
A worked for 5 days and B worked for 7 days
If A and B work together for 5 days they would complete 4×5 =20 units
remaining work =48-20=28 units Now B has to work for 2 more days and if he does it along with C for 2 days.
Then, both would complete (3×2) = 6 units of
work Work left = 28-6= 22 units
Now C completes in 13-2 = 11 days
So, C works 22/1 = 2 unit/day
(efficiency) And B+C does 3 units/day (efficiency) So B does 1 unit/day
B will complete the whole work in 48/1= 48 days