Anil can do a piece of work in 5 days and Ankur in 4 days. How long will they take do the same work, if they work together?

1 Answer

+1 vote
by (30.6k points)
selected by
 
Best answer

The given details are,

Anil can do a piece of work in 5 days

Work done by Anil in 1 day = 1/5

Ankur can do same work in 4 days

Work done by Ankur in 1 day = 1/4

Work done by both in 1 day = 1/5 + 1/4

= (5+4)/20 (by taking LCM for 5 and 4 which is 20)

= 9/20

∴ Total work done together is 1/(20/9) = 20/9 = 2 2/9 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.