A man can do a piece of work in 5 days. He and his son working together can finish it in 3 days. In how many days can the son do it alone?

  1. 6 ½ days
  2. 7 days
  3. 7 ½ days
  4. 8 days

1 Answer

+1 vote
by (58.8k points)
selected by
 
Best answer

we know that,

Number of days man required to do piece of work = 5 days

Number of days his son required to do piece of work = 3 days

Let us consider number of days both man and his son require = x days

∴ We can calculate, work done by man in 1 hour = 1/5

Work done by his son in 1 hour = 1/x

Now, work done by both man and his son together in a 1 hour= 1/3

Now, work done by both man and his son together in 1 hour =1/5 + 1/x = x+5/5x

x+5/5x = 1/3

3x + 15 = 5x

2x =15

x = 15/2

x = 7 ½

∴ Son alone can do work together in 6 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.