A group of men decided to construct a wall in 4 days, but 20 men dropped out every day. Find the total number of men who initially decided to construct the wall, if it was completed in 7 days.


1. 140
2. 145
3. 146
4. 150
5.

1 Answer

0 votes
by (103k points)
selected by
 
Best answer
Correct Answer - Option 1 : 140

Given:

A group of men decided to construct a wall in 4 days.

Formula:

The sum of n terms of AP is the sum(addition) of first n terms of the arithmetic sequence is:

Sum of n terms of AP = n/2[2a + (n – 1)d]

Where “a” is the first term of the AP series and “d” is the common difference between the second and first term-

Concept:

Total work = Total number of men × Total number of days taken to complete the work.

Calculation:

Let the initial number of men be “m”

According to the concept used,

Total work = 4 m

Again, it is given that 20 men dropped out every day, we can write

m + (m – 20) + (m – 40) + (m – 60) + (m – 80) + (m – 100) + (m – 120) = 4 m

According to the formula used,

if 7 is the total number of days taken and common difference is 20, then the sum of total work can be written as,

⇒ (7/2) × [2m + 6(-20)] = 4 m

⇒ (7/2) × [2m - 120] = 4 m

⇒ 7m - 420 = 4 m

⇒ m = 140

∴ The total number of men who initially decided to construct the wall, if it was completed in 7 days is 140.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.