Correct Answer - Option 2 :
10.833
Concept:
The PERT (Project Evaluation and Review Technique) technique is used, when activity time estimates are stochastic in nature.
For each activity, three values of time (optimistic, most likely, pessimistic) are estimated.
-
Optimistic time (to) estimate is the shortest possible time required for the completion of an activity
-
Most likely time (tm) estimate is the time required for the completion of activity under normal circumstances
-
Pessimistic time (tp) estimate is the longest possible time required for the completion of an activity
In PERT expected time of an activity is determined by using the below-given formula:
\({t_e} = \frac{{\left( {{t_o} \;+ \;4{t_m} \;+ {\;t_p}} \right)}}{6}\)
Calculation:
Given:
to = 4 hr, tm = 10 hr, and tp = 20 hr
\({t_e} = \frac{{\left( {{t_o} \;+ \;4{t_m} \;+ {\;t_p}} \right)}}{6}\)
\({t_e} = \frac{{ {{5} \;+ \;4{(10)} \;+ \;{20}} }}{6}\Rightarrow 10.833\;hr\)