Statement (I): In resource levelling, project completion time is not extended provided there is no constraint on availability of resources.

Statement (II): There is generally a constraint against exceeding the project duration time.
1. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
2. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
3. Statement (I) is true but Statement (II) is false
4. Statement (I) is false but Statement (II) is true

1 Answer

0 votes
by (101k points)
selected by
 
Best answer
Correct Answer - Option 2 : Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)

Concept:

The resource is a physical variable required for the completion of activities. It can be material, manpower, machinery, space, money or time resources.

Resource allocation is deciding the resources for each activity.

As here each activity is concerned throughout the project duration, it has a larger bearing on inventory management than resources optimization.

Resource Levelling:

In this method, the activities are so scheduled that the maximum or peak resources requirement does not cross the limit of available resources.

In rescheduling, the available floats are used first, If by doing so, the resources demand is more than the available resources, the duration of some of the activities is increased so that the resource requirement for these activities is decreased. Thus in this process duration initially planned might be increased.

In Resource levelling, project completing time is extended only when the availability of resources is less than the required. But if there is no constraint on availability of resources, project completion time is never extended.

Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)

Resource Optimization:

Resource optimization is the set of processes and methods to match the available resources (human, machinery, financial) with the needs of the organization in order to achieve established goals. Optimization consists in achieving desired results within a set timeframe and budget with a minimum usage of the resources themselves.

It requires us to carry out a statistical analysis of the project buffer consumption using Statistical Process Control (SPC).

Resource Smoothening:

In this method the total project duration is not changed but the activities having float are rescheduled so that a uniform demand for the resources is achieved. So in this case there is constraint on project duration. There is however no constraint on the resources.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.