Which power plant will have high capital initial cost?
1. Diesel power plant
2. Gas power plant
3. Steam power plant
4. Nuclear power plant

1 Answer

0 votes
by (110k points)
selected by
 
Best answer
Correct Answer - Option 4 : Nuclear power plant

Comparison of Power Plant:

Item Nuclear Power Plant Gas & Diesel Power Plant Steam Power Plant
Site These plants are located away from thickly populated areas to avoid radio-active pollution Such plants can be located at any place because they require less space and a small quantity of water. Such plants are located at a place where a supply of water and coal is available, transportation facilities are adequate
Initial cost The initial cost is the highest because of the huge investment in building a nuclear reactor. The initial cost is less as compared to other plants. The initial cost is lower than those of hydroelectric and nuclear power plants.
Operating Cost Except for the hydroelectric plant, it has the minimum running cost because a small amount of fuel can produce a relatively large amount of power Highest among all plants because of the high price of diesel. Higher than hydroelectric and nuclear plants because of the re- requirement of the huge amount of coal.
Cost of fuel transportation Less clean than hydroelectric and diesel power plants. Higher than hydro and nuclear power plants Maximum because a huge amount of coal is transported to the plant site.
Overall efficiency More efficient than a steam power station More efficient than a steam power station. Efficiency is about 35%. Least efficient. Overall efficiency is about 25%.
Standby losses Fewer standby losses. Fewer standby losses. Maximum as the boiler remains in operation even when the turbine is not working.
 

From the above concept, it is clear that the Nuclear power plant has a high initial cost.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.