Which of the following CANNOT be covered under the head of initial cost of power plant?
1. Equipment cost
2. Maintenance cost
3. Land cost
4. Building cost

1 Answer

0 votes
by (237k points)
selected by
 
Best answer
Correct Answer - Option 2 : Maintenance cost

Concept:

Running or operational cost of the power system:

  • The concept of the running cost is quite simple. It solely depends on the number of units produced or generated.
  • In a power generating plant, the main operational cost is the cost of fuel burnt per unit of electrical energy generation.
  • The cost of lubricating oil, maintenance, repairs, and salaries of operating staff are also accounted for the operating cost of the plant.
  • Since these charges are proportional to the number of units generated. For generating more units of electrical energy the required running expenditure is more and vice versa.

 

Capital cost:

  • Initial cost or fixed cost is essentially capital costs and land.
  • Fixed cost is the cost that is independent of max demand and units generated.
  • The fixed cost is due to the annual cost of a central organization, interest on the capital cost of land, and salaries of higher officials.

 

Explanation:

Equipment cost, land cost, and building cost are the part of capital cost whereas maintenance cost is the part of running cost.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.