A man can paint a house working every day in 20 days. He decides to take a break for 1 day after every 4 days. In how many days will he complete the work now?
1. 40
2. 25
3. 30
4. 24

1 Answer

0 votes
by (105k points)
selected by
 
Best answer
Correct Answer - Option 4 : 24

Given:

A man can paint a house working every day in 20 days

Concept Used:

Total work = Efficiency × Time taken

Calculation:

According to the question, we have

He decides to take a break for 1 day after every 4 days

The number of days to take break = (20/4 - 1) = 5 - 1 ⇒ 4

Now,

The total number of days completes the work = 20 + 4 ⇒ 24

∴ The total number of days completes work done is 24 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.