14 workers can construct a wall in 20 days then in how many days 20 workers will construct 2 such walls?
1. 20 days
2. 35 days
3. 28 days
4. 21 days 

1 Answer

0 votes
by (113k points)
selected by
 
Best answer
Correct Answer - Option 3 : 28 days

Formula used:

Time is taken = Total work/Efficiency

Calculation:

As, 14 workers can construct a wall in 20 days

So, 1 worker construct a wall in 20 × 14 = 280 days

⇒ 20 works construct a wall in \({280 \ \over 20}\)= 14 days

⇒ 20 workers construct 2 such walls in 14 × 2 = 28 days

∴ 20 workers construct 2 walls in 28 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.