Correct Answer - Option 4 : 15 days
Given:
Number of workers = 21
Days = 25
New workers deployed = 14
Workers after new Joinings = 14 + 21 = 35
Formula Used:
(Workers1 × Days1)/(Work1) = (Workers2 × Days2)/(Work2)
Calculation:
(21 × 25)/1 = (35 × Days)/1
By cross multiplication:
⇒ Days = 15
∴ After deploying 14 new workers work will be done in 15 days.
The correct option is 4 i.e. 15 days