Minimum work required
Wmin = Availability increase
= h2 – h1 – T0(s2 – s1)
= mcp (T2 – T1) – T0 Δs
= 1 × 1.005 (523 – 294) – 293 × 0.064647
= 211.2 kJ/kg
Actual work required (Wact) = 230.145 kJ/kg
∴ Irreversibility = T0 Δs
= 293 × 0.064647
= 18.942 kJ/kg